Nov 2008 T2 Hardware
Things that can happen whenever:
- configure PDUs power strips
- install power cords to PDUs
- label needed network cables
- get hostnames registered (figure out IPs to use)
- add nodes to ROCKS
- make labels for nodes, pdus, racks
Nov 11 Expand Switch Stack
On this Tuesday, we'll put the 3 new switches into the main stack. One switch will replace unit 1 and the other 2 will be located in rack 106 to expand the stack from 5 to 7 units.
Things that need to be ready to do this:
- switches, check firmware version, need config
- rack 106
- cx4 stacking cables. need to check existing and see which will be replaced
- modules, need to check which will need to be modified
Nov 18 Install New Computers
On this Tuesday, hopefully we can rack and install the computers.
--
TomRockwell - 06 Nov 2008